How to Install a Tower Crane? Step by Step Assembly Process

Tower crane installation step by step: soil survey and foundation, mobile crane, mast, slewing unit, counter-jib and counterweights, jib and load test.

13.04.2026 Turkish Tower Cranes 10 dk

Tower crane installation consists of a preparation phase and six assembly steps: soil survey and foundation, positioning the mobile crane, erecting the base and mast sections, fitting the slewing unit and cab, the counter-jib with the first counterweights, mounting the jib, and finally the remaining counterweights, limit settings and load test. The order cannot be changed: splitting the counterweights into two stages, before and after the jib goes on, is what keeps the crane from tipping during assembly. Below we go through each step in the order Turkish Tower Cranes assembly crews follow.

PREPARATION: GROUND AND PLANNING

Work starts weeks before installation day.

  1. Site survey: The crew measures the position and level of the crane base, the area where the mobile crane will stand and the bearing capacity of the ground there, the access route for the delivery trucks, overhead power lines, and whether the jib will swing over neighbouring buildings.
  2. Soil survey and structural calculation: Can the ground at the crane position carry the fully loaded weight of the crane and the wind load? Our engineers calculate the bearing capacity.
  3. Foundation and anchoring: If a fixed base is used, the crane's fixing angles are set into the foundation concrete with millimetre precision. A levelling error at this stage grows as the crane rises and can end with the crane tipping over, which is why laser measuring devices are used. Assembly does not start until the foundation concrete has gained strength; how long that takes depends on the weather.

HOW IS A TOWER CRANE FOUNDATION DESIGNED?

The crane foundation is calculated separately from the building's foundation. The inputs are the soil survey report and the foundation loads given by the manufacturer, which differ from model to model. A shallow foundation is enough on most sites; on alluvial ground or ground with a liquefaction risk, a piled foundation may be needed. Lighter models put less load on the foundation, so a piled solution needs fewer piles. We provide the foundation design and the load data; building the foundation usually stays with the site.

STEP 1: POSITIONING THE MOBILE CRANE

A tower crane cannot erect itself (except when climbing). A mobile crane comes to site to lift the parts. Its capacity must be enough to lift the heaviest tower crane component (usually the slewing unit or the counter-jib) to the height of the tower. Its position is fixed during the site survey; if there is no room on site, a road closure permit or night work may be needed.

STEP 2: ERECTING THE BASE AND MAST

Once the concrete has cured, the base is connected to the anchors and the first mast sections are erected.

  • Climbing cage: If the crane will be raised later, a climbing (telescoping) cage is fitted at a set level of the mast. Its hydraulic system lets the crane raise itself.

STEP 3: SLEWING UNIT AND CAB (THE MOST CRITICAL PART)

The gear system that turns the crane (the slewing unit) and the operator's cab are placed on top of the mast, in one or two pieces. This is usually the heaviest and most delicate component. While it is being seated, the bolts must be tightened with a torque wrench to the specified newton-metre value.

STEP 4: COUNTER-JIB AND FIRST COUNTERWEIGHTS

This is where the physics comes in. The counter-jib goes on first.

  • CAUTION: Right after the counter-jib is mounted, and BEFORE the jib, the calculated amount of counterweight must be placed on it. Why? Because a long, heavy jib is about to be fitted at the front. With no weight at the back, the crane would tip forward while the jib is being mounted. Not all the counterweights go on at this stage, only enough to balance the jib.

STEP 5: MOUNTING THE JIB

This depends on the crane type:

  • Hammerhead: The jib is fully assembled on the ground, its tie bars are prepared, and it is lifted in one piece.
  • Flat top: Jib sections can be added in the air one by one or in blocks. Once the jib is pinned in place, on hammerhead cranes the tie bars are connected to the tower head.

STEP 6: FINAL BALANCING AND CALIBRATION

After the jib is on, the remaining counterweights are placed on the counter-jib. The crane is now physically complete, but the job is not finished.

  • Limit switch settings: Does the hook stop at the top? Does the system cut out when the load limit is exceeded?
  • Load test: Static and dynamic load tests are carried out.

HOW LONG DOES INSTALLATION TAKE?

The assembly itself depends on the crane model, the erection height and the site conditions, and is calculated for each site. The schedule is usually set by the preparation rather than the assembly: the foundation concrete gaining strength, permits for the oversize load and any road closure, getting the mobile crane onto the site, and a day when the wind allows the work. A duration given without a site survey will change on site.

AFTER INSTALLATION: CLIMBING AND DISMANTLING

As the building rises, the crane raises itself with the climbing cage; no mobile crane is needed for this. If the free-standing height will be exceeded, the crane is tied to the building and the tie points are planned together with the building's structural design. At the end of the project, dismantling is planned just like assembly: the same wind limits and the same need for a mobile crane apply. By then the building is up and the site is crowded, so the dismantling plan should be made at the start of the project.

Details of our assembly service, including the site survey, tie-in planning and climbing operations, are on the Assembly & Dismantling page; the free-standing and under-hook heights of TTC models are on the product pages.

CONCLUSION

Tower crane installation is not a job to be rushed. If the wind speed exceeds the assembly limit set in the crane manufacturer's instructions, assembly is stopped. At Turkish Tower Cranes we carry out installation under the supervision of certified erectors and occupational safety specialists, with a zero-error approach.